Question 1: (17 marks) The data given in Table 1 shows PV, EV, and AC values in thousands of dollars for the first 30 weeks
Question 1: (17 marks)
The data given in Table 1 shows PV, EV, and AC values in thousands of dollars for the first 30 weeks of a projects execution before its completion. Answer the following questions:
a. Using three different pen colors, draw a graph showing the curves PV, EV, and AC. Label appropriately the curves and the x-axis and y-axis (5 marks);
b. Indicate the intervals of time where the project is on schedule, going faster or slower than the planned schedule (4 marks);
c. Indicate the intervals of time where the project is on budget, under or over the planned budget (4 marks);
d. Evaluate the budget gain or loss that occurred on week 15 in dollars (2 marks);
e. Evaluate the schedule status on week 25 (2 marks).
Activity ID | Week Number | PV $(000) | EV $(000) | AC $(000) |
A | 5 | 7 | 5 | 2 |
B | 10 | 13 | 10 | 7 |
C | 15 | 18 | 15 | 12 |
D | 20 | 20 | 20 | 20 |
E | 25 | 22 | 25 | 28 |
F | 30 | 27 | 30 | 33 |
Question 2: (13 marks)
Discuss five approaches to reducing the critical path.
Which is the most effective? And why?
Which is the most difficult to achieve? And why?
Question 3: (9 marks)
The following work breakdown table displays the tasks in a particular project.
- Construct a network diagram using the information in the table;
- Identify the critical path;
- Calculate the planned duration of the project in days;
- Calculate the total float of the project in days.
Activity
ID
Duration
In days
Immediate
Predecessor
A
5
None
B
4
A
C
3
A
D
6
B, C
E
4
B
F
2
D, E
Question 4: (11 marks)
What is the Work Breakdown Structure (WBS)? Who is responsible for creating it? And what is its purpose? (5 marks).
Provide an example of WBS for a project of your own. The example should include the following:
- A project title; (1.5 marks)
- Outlined relevant phases; (1.5 marks)
- Activities are to be named and numbered appropriately; (1.5 marks)
- Activities are to be joined appropriately and logically. (1.5 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started