Question 1 3 of 7 5 Which of the following approaches to establishing a baseline is MOST preferred? A A similarly sized project B A
Question of
Which of the following approaches to establishing a baseline is MOST preferred?
A A similarly sized project
B A seriously considered project alternative
C Existing conditions
D Preliminary design