Question 1 (5 points) If the likelihood that the requirements for a software development project will change after design is 0.4, and the cost to
Question 1 (5 points) If the likelihood that the requirements for a software development project will change after design is 0.4, and the cost to redesign to new requirements is $30,000, what is the risk exposure