Question 1 College of Excellence is considering building a new multipurpose auditorium on campus. The complex should provide a new conference room, expanded office space,
Question 1
College of Excellence is considering building a new multipurpose auditorium on campus. The complex should provide a new conference room, expanded office space, classrooms, and multimedia facilities. The following activities would have to be undertaken before construction can begin.
Activity | Description | Immediate Predecessor | Time (weeks) |
A | Survey building site | -------- | 6 |
B | Develop initial design | ---------- | 8 |
C | Obtain board approval | A,B | 12 |
D | Select architect | C | 4 |
E | Establish budget | C | 6 |
F | Finalize design | D,E | 15 |
G | Obtain financing | E | 12 |
H | Hire contractor | F,G | 8 |
- Draw a CPM for the above project network, indicating early start, early finish, late start and the late finish.
- What are the critical the path of the network?
- What is the expected completion time for the project?
- What is the importance of slack time?
- Calculate the slack time of each activity (use a table to illustrate the LS, ES and slack for each activity).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started