Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 1: Table 1 shows the planned tasks of a specific phase (irrelevant of the software process adopted) for a small software project). Note 1:

Question 1: Table 1 shows the planned tasks of a specific phase (irrelevant of the software process adopted) for a small software project). Note 1: All times are in days. Note 2: The project workflow proceeds from Task 1 to Task 11.

Table 1: Planned tasks of a specific project phase. Task ID Task Name Estimated Time Predecessors 1 Task 1 2 2 Task 2 1 3 Task 3 5 4 Task 4 1 3 5 Task 5 3 2 6 Task 6 1 3 7 Task 7 3 1 8 Task 8 1 6 9 Task 9 1 5,3,7 10 Task 10 1 7 11 Task 11 2 4,8,9,10

a. Draw the network diagram for executing the tasks shown in Table 1and note how long they are. b. What is (are) the critical path(s) for this phase and how long it (they) takes in day?

c. What is the shortest possible time it will take to complete this project phase?

d. [2 points] Calculate the free the total float (slack) and for each of the activities of the network.

Activity ID Activity Name Free Slack Total Slack 1 Task 1 2 Task 2 3 Task 3 4 Task 4 5 Task 5 6 Task 6 7 Task 7 8 Task 8 9 Task 9 10 Task 10 11 Task 11

e. Assume that Task 5 took two extra days. Would the project completion time change? Explain. f. Assume that Task 7 took one extra day. Would the project completion time change? Explain.

Question 2

Three-point estimating

Instead of providing activity estimates as a discrete number, such as four weeks, its often helpful to create a three-point estimate. An estimate that includes an optimistic, most likely, and pessimistic estimate. -Optimistic (to) -Most Likely (tm) -Pessimistic (tp)

Use the following equation to calculate the expected duration:

Beta Distribution

For Activity A:

Optimistic = 4 hours , Most Likely = 8 hours , Pessimistic = 16 hours The Standard Deviation is a measure of variability from the mean and is defined as (p - o)/6 so in the example above Calculate the three point estimate and the standard deviation of activity A. Explain your answer.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Database Systems

Authors: Ramez Elmasri, Sham Navathe

4th Edition

0321122267, 978-0321122261

More Books

Students also viewed these Databases questions

Question

Explain exothermic and endothermic reactions with examples

Answered: 1 week ago

Question

Write a short note on rancidity and corrosiveness.

Answered: 1 week ago

Question

What are Decision Trees?

Answered: 1 week ago

Question

What is meant by the Term Glass Ceiling?

Answered: 1 week ago