Question

1 Approved Answer

Question 13 (4 points) Order the four below in terms of the sequence in which they would typically be performed (1 being the first and

Question 13(4 points)

Order the four below in terms of the sequence in which they would typically be performed (1 being thefirstand 4 being last).

A-Develop project schedule

B-Create WBS

C-Determine budget

D-Create network diagram

Question 14(4 points)

Which of the following could characterize the project's critical path?

A-The path with the greatest number of activities

B-The path with the least number of activities

C-The path whose schedule risk is the highest

D-The path whose schedule risk is the least

Question 16(4 points)

The risk register can contain

A-Project risks

B-Potential risk responses

C-Risk urgency

Question 18(4 points)

Qualitative risk analysis is used to

A-Determine the impact of risk on quality

B-Determine the quality of the risk identification effort

C-Prioritize individual project risks

D-Determine the quality of the overall risk management processes

E-Lists all risks which are expected to be addressed in the near term

Question 21(4 points)

Contract penalty clauses are a way to

A-Completely avoid risk

B-Transfer risk

C-Escalate risk

D-Accept risk

Question 23(4 points)

A project plan is for constructing 100 tool booths along a stretch of highway in 5 months at a cost of one million dollars.Assume that the plan is for uniform construction rate and spending. Three months after project start, 50% of the toll booths have been completed. What is the project's approximate SPI at this point in time (three months after project start)?

Question 23 options:

0.83

0.5

1.2

1

Question 26(4 points)

Crashing a critical path activity

A-Will always reduce the project schedule/duration

B-May not necessarily reduce the project schedule/duration

C-Will always result in another critical path being created

D-Will always significantly increase the project's risk

Question 27(4 points)

Activity P on a project has exactly 5 predecessors A, B, C, D, and E whose early finish days are 22, 32, 38, 50, and 32, respectively. (Here"day"means"days after project start".) What is the early start day of P?

A-33

B-23

C-51

D-22

Question 29(5 points)

This question is associated withPart 2in your assignment. Which of the following is the answer you got forPart 2- the probability of the project completing in less than 34 weeks (based on modeling theentire schedule)?

A-About 90%

B-About 70%

C-About 40%

D-Less than 5%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foundations of Lodging Management

Authors: David K. Hayes, Jack D. Ninemeier, Allisha A. Miller.

2nd edition

132560895, 978-0132560894

More Books

Students also viewed these General Management questions