QUESTION 19 The jobs listed below have not yet been scheduled. Using the S/RO technique, in what sequence would you schedule these jobs? Job Slack
QUESTION 19
The jobs listed below have not yet been scheduled. Using the S/RO technique, in what sequence would you schedule these jobs?
Job | Slack | Remaining Operations |
A | 3 | 1 |
B | 10 | 11 |
C | 5 | 4 |
D | 12 | 6 |
E | 8 | 8 |
A. | A-D-C-E-B | |
B. | E-C-D-A-B | |
C. | A-C-D-E-B | |
D. | B-E-C-D-A | |
E. | A-C-E-B-D |
QUESTION 24
The following set of jobs must be processed serially through a two-step system. If Johnson's Rule is used to sequence the jobs then the order in which the jobs would be performed is
Job | Process 1 | Process 2 |
A | 12 | 9 |
B | 8 | 11 |
C | 7 | 6 |
D | 10 | 14 |
E | 5 | 8 |
A. | D-E-B-A-C | |
B. | C-B-E-D-A | |
C. | A-B-C-D-E | |
D. | E-B-D-A-C |
4 points
QUESTION 25
The following set of jobs must be processed serially through a two-step system. The times at each process are in hours. If Johnson's Rule is used to sequence the jobs then the makespan time (in hours) for all jobs is
Job | Process 1 | Process 2 |
A | 12 | 9 |
B | 8 | 11 |
C | 7 | 6 |
D | 10 | 14 |
E | 5 | 8 |
A. | 53 hours. | |
B. | 95 hours. | |
C. | 42 hours. | |
D. | 90 hours. |
4 points
QUESTION 26
The following set of jobs must be processed serially through a two-step system. The times at each process are in hours. If Johnson's Rule is used to sequence the jobs then Job C would start processing on operation 2 at
Job | Process 1 | Process 2 |
A | 12 | 9 |
B | 8 | 11 |
C | 7 | 6 |
D | 10 | 14 |
E | 5 | 8 |
A. | hour 47. | |
B. | hour 53 | |
C. | hour 13. | |
D. | hour 26. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started