QUESTION 2 Omicronie Inc., provides project management services in the construction industry for a variety of clients. Each job is uniquely different and the Lynn
QUESTION 2
Omicronie Inc., provides project management services in the construction industry for a variety of clients. Each job is uniquely different and the Lynn Deberghie, the company's accountant decided to use job costing for the allocation of costs on the current jobs. She will be using construction-labour hours as the basis for overhead allocation. In December 2021, she estimated the following amounts for 2022:
Direct Materials | $15,650,000 |
Construction Labour | $11,200,000 |
Overhead | $9,800,000 |
Construction Labour-Hours | 600,000 |
The following results for the first quarter of 2022 for the following jobs that were started and completed in that same period.
Library | Dental Office | Medical Building | |
Direct Materials | $924,000 | $1,134,600 | $1,525,000 |
Construction Labour-Hours | 76,400 | 47,200 | 19,500 |
- Calculate the predetermined overhead allocation rate for 2022 and apply overhead to the three (3) jobs. (6 marks)
- Calculate the cost of each job.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started