Question 2 Oriole Construction Company had a contract starting April 2018, to construct a $24300000 building that is expected to be completed in September 2020,
Question 2
Oriole Construction Company had a contract starting April 2018, to construct a $24300000 building that is expected to be completed in September 2020, at an estimated cost of $22300000. At the end of 2018, the costs to date were $10927000 and the estimated total costs to complete had not changed. The progress billings during 2018 were $510000 and the cash collected during 2018 was 3230000. Oriole uses the percentage-of-completion method.
For the year ended December 31, 2018, Oriole would recognize gross profit on the building of:
a)$0.
b)$980000.
c)$899342.
d)$11373000.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started