QUESTION 25 (10 points) - Efficiency Measurements We have a hypothetical business process with three consecutive resources. Information about important aspects of the business is presented in the table/template below. Note that the template shows you the recommended steps for calculating various efficiency measurements. You do not need to fill in the shaded cells. Make sure to show equations and calculations. Resource 1 2 3 PR Processing time (min/unit/worker) 5 NJ 3 Number of workers 3 1 2 Hourly wage ($/hour/worker) 20 16 18 Capacity (units/hour) Demand (units/hour) 35 35 35 35 Flow Rate (units/hour) Cycle time (min) Efficiency Measurements 1 2 3 PR Paid time (min/unit) Labor cost ($/hour) Cost of direct labor ($/unit) CODL Labor content (min/unit) LCT Idle time (min/unit) IDT & TIDT Employee utilization & ALU Average labor utilization (ALU) Average labor utilization (ALU) (a) [2] Find the flow rate and cycle time, assuming abundant input. (b) [2] Find the cost of direct labor (CODL) and make a statement about it. (c)[2] Find the labor content (LCT) and make a statement about it. (d) [4] Find the average labor utilization (ALU) in three ways (Module 04 - Slide 47), and make a statement about it. For this part, make sure to show detailed calculations outside the table. Note: in this question, we focus on efficiency of time usage and disregard wage-rate differences; in the future, you can modify the calculations to measure efficiency of money usage.Resource N PR Processing time (min/unit/worker) 5 2 Number of workers 2 Hourly wage ($/hour/worker) 20 16 18 Capacity (units/hour) 36 30 40 30 Demand (units/hour) 35 35 35 35 Flow Rate (units/hour) 30 30 30 30 Cycle time (min) 2 2 2 2 Efficiency Measurements 2 3 PR Paid time (min/unit) 6 2 A Labor cost ($/hour) 60 16 36 Cost of direct labor ($/unit) CODL 3.733333333 Labor content (min/unit) LCT 5 2 3 Idle time (min/unit) IDT & TIDT 0 Employee utilization & ALU 0.8333333333 0.75 Average labor utilization (ALU) 0.8333333333 Average labor utilization (ALU)