Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question 3: Project Scheduling [28 marks] (a) Consider Table 1 that shows the schedule of testing activities of a software project. Activity ID Predecessor Duration
Question 3: Project Scheduling [28 marks] (a) Consider Table 1 that shows the schedule of testing activities of a software project. Activity ID Predecessor Duration (weeks) A NONE 5 . A 3 A 10 D B 3 E D 5 F C.E 6 G F 8 H F 1 1 G.H 5 - Table 1: Testing phase [2] [2] (a.1) Draw a Gantt chart for the above project schedule. (a.2) Draw a PERT diagram for the above project schedule. (1.3) What is the earliest completion time for the project? (a.4) What is the Slack Time of each task and each event? (2.5) What is the critical path of the project? (2.6) What would happen to the project if task C was delayed by 3 weeks? [8] [2]
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started