Answered step by step
Verified Expert Solution
Question
1 Approved Answer
QUESTION 4 [8] The baseline time estimate for the completion of a sports field at centurion primary is 20 weeks and the baseline cost estimate
QUESTION 4 [8] The baseline time estimate for the completion of a sports field at centurion primary is 20 weeks and the baseline cost estimate is R100 000. Assume that the risk likelihood for the project is 0.3 , if the risk is materialized the project would be delayed by 6 weeks and it will cost R 20000 more. 4.1. Calculate risk time (RT) (2) 4.2. Risk cost (RC), (2) 4.3. Expected project completion time (ET) (2) 4.4. Expected project completion cost (EC). (2)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started