Question 4 A company forecast weekly demand for certain equipment as follows, Week 1 2 3 4 5 6 7 8 9 10 11 Demand
Question 4
A company forecast weekly demand for certain equipment as follows,
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
Demand | 8 | 10 | 7 | 6 | 15 | 5 | 4 | 12 | 9 | 14 | 5 |
Week | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 |
Demand | 7 | 18 | 4 | 11 | 10 | 6 | 8 | 5 | 16 | 14 | 4 |
Each equipment cost $100, it costs $600 to place an order and get delivery, and holding cost is 10% of the value a week. Design a reasonable ordering policy for the equipment. (Part a-d)
a)For the first order, how many weeks of demand should be combined?
Group of answer choices
4
2
3
5
None of them
b)For the first combined order, what is the average weekly variable cost (i.e., order cost and holding cost)?
Group of answer choices
$305.00
$325.00
$390.00
$250.00
None of them
c)How many combined orders could we decide now with the available demand data?
Group of answer choices
5
3
4
6
None of them
d)How much is the average weekly variable cost (i.e., order cost and holding cost) for all the combined orders with the available demand data?
Group of answer choices
$327.11
$303.65
$348.64
$362.13
None of them
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started