Question 4 The following estimates in terms of working days were prepared for a new project: Activity Preceding Activity Most optimistic time (days) Most probable

Question 4

The following estimates in terms of working days were prepared for a new project:

Activity

Preceding Activity

Most optimistic time (days)

Most probable time (days)

Most pessimistic time (days)

A

B

C

D

E

-

-

-

A

B, D

4

3

6

3

2

6

6

8

4

3

8

9

16

5

4

REQUIRED:

MARKS

4.1

Calculate the expected duration of each of the above activities

5

4.2

Prepare a network diagram and indicate the critical path.

5

Total

10

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic management concepts

Authors: Fred david

13th Edition

9780136120988, 136120997, 136120989, 978-0136120995

More Books

Students also viewed these General Management questions