Answered step by step
Verified Expert Solution
Question
1 Approved Answer
QUESTION 5 [10] For a particular work package, the budgeted cost as of 1 October is R20 000. Assume that as of 1 September, you
QUESTION 5 [10] For a particular work package, the budgeted cost as of 1 October is R20 000. Assume that as of 1 September, you as the project manager determines that only 85% of the scheduled work has been completed and the actual expense is R22 000 . 5.2.1. Determine the BCWP, BCWS, and ACWP. (3) 5.2.2. Calculate AV,SV,CV,SPI, and CPI for the work package. Explain the progress made. (7)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started