Question 5: BC Analysis A city government is considering increasing the capacity of the current wastewater treatment plant. The estimated financial data for the
Question 5: BC Analysis A city government is considering increasing the capacity of the current wastewater treatment plant. The estimated financial data for the project is as follows: Description Capital Investment Project Life Annual Benefits Annual Costs Salvage Value Data $1,000,000 20 years $220,000 $80,000 $40,000 7.5% Discount Rate (interest rate) Calculate the benefit-cost ratio for this capacity expansion project.