Question
1 Approved Answer

Question 52 Consider the following project details and estimates: Activity Normal time (days) ABCDEFG A 15 15 19 20 9 6 14 9 8

  

Question 52 Consider the following project details and estimates: Activity Normal time (days) ABCDEFG A 15 15 19 20 9 6 14 9 8 Total Crash time (days) 12 14 4500 4 000 2 500 1700 4300 2 600 1800: direct cost 21 400 5 5 9 6 The network diagram for the project is shown below: Normal cost Crash cost ($) ($) E 14 5250 4 500 4500 1860 5350 3440 3400 28 300 S 1 points QUESTION COMPLETION STATUS: The network diagram for the project is shown below: A 15 B 19 C 9 E 14 Iz FO .8 Following a normal schedule, what is the estimated time to complete the project? O a. 30 days O b. 17 days O c. 29 days Od. 28 days SWA

Step by Step Solution

3.40 Rating (150 Votes )

There are 3 Steps involved in it

Step: 1

First lets find the critical path Lets list all the po... blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

More Books

Students explore these related Economics questions