Question 6 of 1 0 is defined as the amount of time a schedule activity can be delayed without delaying the early start of any

Question 6 of 10
is defined as "the amount of time a schedule activity can be delayed without delaying the early start of any successor or violating a schedule constraint."
a. Total float
b. Lag time
c. Free float
d. Lead time
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Concepts

Authors: David Kroenke, David Auer, Scott Vandenberg, Robert Yoder

8th Edition

013460153X, 978-0134601533

More Books

Students also viewed these Databases questions

Question

How does this scenario illustrate the process of mainstreaming?

Answered: 1 week ago