QUESTION 6 When the project is at a stage where the PM is monitoring project performance to identify variances from the project plan, what process
QUESTION 6
- When the project is at a stage where the PM is monitoring project performance to identify variances from the project plan, what process group is it in?
A.
Initiating
B.
Planning
C.
Executing
D.
Monitoring/controlling
E.
Closing
QUESTION 7
- What is the first thing that should happen when a new change request comes in?
A.
It should be evaluated for feasibility
B.
It should be assigned a tracking number
C.
A determination is made as to whether the person or entity submitting the change request is a valid stakeholder in the project
D.
The project sponsor is notified
QUESTION 8
- When would a PM make a decision to crash a project?
A.
When it's clear the project's going to fail
B.
When there is a demand to complete the project more quickly
C.
When project team members are not busy
D.
When budget is no object
QUESTION 9
- When considering crashing a project, which activities should be included?
A.
All project activities
B.
Only those activities not on the critical path
C.
Only those activities on the critical path
D.
Only those activities that could benefit from the crashing effort
QUESTION 10
- Of the following, which is the most likely to be impacted by change?
A.
Scope
B.
Budget
C.
Time
D.
Quality
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started