Question 7 4 If the project manager of a medium - sized apartment housing construction project wanted to develop an appropriate risk response to the
Question
If the project manager of a mediumsized apartment housing construction project wanted to develop an appropriate risk response to the risk that a fire may destroy or damage the partially completed apartment complex during the construction process, the two most likely risk responses that would be employed would be:
risk avoidance and retaining of risk
retaining of risk and sharing of risk
risk mitigation and transfer of risk
risk avoidance and sharing of risk
retaining of risk and contingency planning
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started