Question
Question #8: Project Financials You are the project manager and your boss has asked you to provide a status based project earned value management.You are
Question #8: Project Financials
You are the project manager and your boss has asked you to provide a status based project earned value management.You are managing a project that is creating Webpages.You have a budget of $200,000.Each webpage is expected to cost $10,000 and you are producing 20 Web Pages.Your duration of the project is scheduled for 20 weeks.At week 10 you have only produced 8 webpages.You should have produced 10 of the 20 at this point. Your actual cost is $90,000 and your planned value at this point in the project is $100,000.Please update the chart below with the correct information.
oBudget (BAC) = $200,000
oDuration = 20 weeks (Delivers one page per week)
oActual Cost = $90,000
oPlanned Value at this point in the project = $100,000 (Planned % complete * BAC)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started