Question

1 Approved Answer

Question #8: Project Financials You are the project manager and your boss has asked you to provide a status based project earned value management.You are

Question #8: Project Financials

You are the project manager and your boss has asked you to provide a status based project earned value management.You are managing a project that is creating Webpages.You have a budget of $200,000.Each webpage is expected to cost $10,000 and you are producing 20 Web Pages.Your duration of the project is scheduled for 20 weeks.At week 10 you have only produced 8 webpages.You should have produced 10 of the 20 at this point. Your actual cost is $90,000 and your planned value at this point in the project is $100,000.Please update the chart below with the correct information.

oBudget (BAC) = $200,000

oDuration = 20 weeks (Delivers one page per week)

oActual Cost = $90,000

oPlanned Value at this point in the project = $100,000 (Planned % complete * BAC)

image text in transcribed
Earned Value management Values Budget at Completion Actual Cost (AC) Duration Planned Value (PV) Earned Value (EV) SPI SV CPI CV EAC VAC ETC

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Research Methods And Design In Sport Management

Authors: Damon Andrew, Paul M. Pedersen, Chad McEvoy

1st Edition

073607385X, 978-0736073851

More Books

Students also viewed these General Management questions

Question

3. Explain the forces that influence how people handle conflict

Answered: 1 week ago