Question
Question #8: Using the following task list, calculate the critical path of the Disney Expedition Everest project. Show your work by providing your network diagram.
Question #8:
Using the following task list, calculate the critical path of the Disney Expedition Everest project. Show your work by providing your network diagram. You may use a drawing application to produce your network diagram, draw it on paper and paste a photo of your drawing here, or use PowerPoint or Visio.
Ensure that you explicitly state the critical path of your project and show your work. (4 points)
Task ID | Task | Duration | Predecessor |
1 | Plan Expedition Everest project | 10 months | |
2 | Research Nepal Environment and Artifacts | 8 months | 1 |
3 | Design Mountain | 6 months | 1 |
4 | Design Roller Coaster | 10 months | 3 |
5 | Design Yeti | 8 months | 4 |
6 | Design Village | 4 months | 2 |
7 | Approve Design | 1 month | 3, 4, 5, 6 |
8 | Construct Mountain | 14 months | 7 |
9 | Construct Roller Coaster | 12 months | 8 |
10 | Construct Yeti | 12 months | 9 |
Task ID | Task | Duration | Predecessor |
11 | Construct Village | 6 months | 8 |
12 | Inspect Ride | 1 month | 8, 9, 10, 11 |
13 | Test Ride | 3 months | 12 |
14 | Advertise the Opening of Expedition Everest | 6 months | 7 |
15 | Open Ride | 0 months | 13, 14 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started