Answered step by step
Verified Expert Solution
Question
1 Approved Answer
QUESTION FOUR [25] 4.1 The following table represents a project you are working on. Activity Predecessor Time (days) Time Time (days) Optimistic (days) Pessimistic Most
QUESTION FOUR [25]
4.1 The following table represents a project you are working on.
Activity Predecessor Time (days) Time Time (days) Optimistic (days) Pessimistic Most likely 15 18 25 15 18 20 C a,b 6 10 12 d C 18 24 26 13 19 25 12 18 23 d 15 17 19 h f,g 22 25 30 ef 11 15 17 4.1 Calculate the time (t) and variance (v) for each activity. (8) 4.2 Describe how the network diagram (AON) can be used for the information presented above. (diagram not required) (12) 4.3 Identify the paths and the critical path.Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started