QUIZ 1: SCHEDULE MANAGEMENT Question 1 1pts A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has
QUIZ 1: SCHEDULE MANAGEMENT
Question 1 1pts
A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the late finish for the Plant Posts activity?
Activity | Optimistic time | Most Likely time | Pessimistic time | Predecessor |
Corner Posts | 4 | 5 | 6 | -- |
String Line | 7 | 8 | 9 | -- |
Dig Holes | 10 | 12 | 14 | Corner Posts |
Plant Posts | 11 | 14 | 17 | String Line |
Weld Top Bar | 8 | 11 | 14 | String Line |
Paint | 9 | 11 | 13 | Dig Holes, Plant Posts |
Tack Wire | 9 | 12 | 16 | Weld Top Bar |
Group of answer choices
13.3 days
8 days
20.83 days
22 days
Flag question: Question 2
Question 2 1pts
A project has three critical paths. Which of the following best describes how this affects the project?
Group of answer choices
It makes it more expensive
It makes it easier to manage
It increases the project risk
It requires more people
Flag question: Question 3
Question 3 1pts
An activity has an early start of day 3, a late start of day 13, an early finish of day 9, and a late finish of day 19. The activity:
Group of answer choices
Is on the critical path
Has a lag
Is progressing well
It is not on the critical path
Flag question: Question 4
Question 4 1pts
At a burst point in a backward pass, the largest succeeding late start becomes the late finish for that node.
Group of answer choices
True
False
Flag question: Question 5
Question 5 1pts
At a merge point in a forward pass, the largest preceding early finish becomes the early start for that node.
Group of answer choices
True
False
Flag question: Question 6
Question 6 1pts
Based on the activity network pictured, what is the BEST statement?
Group of answer choices
Before starting Activity C, Activity A and Activity B must be completed.
Before starting Activity C, Activity A and Activity D must be completed.
Before starting Activity E, Activity A and Activity B need to be completed.
Before starting Activity D, Activity A and Activity B need to be completed.
Flag question: Question 7
Question 7 1pts
Calculation of late finish dates and late start dates for the uncompleted portion of the project is called ________________
Group of answer choices
Schedule compression
A backward pass
A forward pass
An arrow diagram
Flag question: Question 8
Question 8 1pts
In a finish-to-start relationship between predecessor and successor activities, a project manager decides to schedule a successor activity five days before its predecessor is complete. This is accomplished by providing five days of:
Group of answer choices
Load
Fast tracking
Lag
Lead
Flag question: Question 9
Question 9 1pts
In a project, activity A has a duration of 4 days and begins on the morning of Monday the 4th. The successor activity, B, has a Finish-to-Start (FS) relationship with A. The Finish-to start relationship has a 2 days of lag. Activity B has a duration of 3 days. If Saturday and Sunday are non-working days, which of the following statements s true?
Group of answer choices
Activity B will be completed by end of the day on Thursday, 14th.
Activity B will be completed by end of the day on Tuesday, 12th.
Activity B will be completed by end of the day on Friday, 15th.
Activity B will be completed by end of the day on Wednesday, 13th.
Flag question: Question 10
Question 10 1pts
Lag means
Group of answer choices
The amount of time an activity can be delayed without delaying the early start date of its successor.
The amount of time an activity can be delayed without delaying the project finish date.
Waiting time
The product of a forward and backward pass.
Flag question: Question 11
Question 11 1pts
Most project management software packages use a method of constructing a project schedule network diagram known as:
Group of answer choices
Precedence Diagramming Method
Project Diagramming Method
Activity Diagramming Method
Critical Diagramming Method
Flag question: Question 12
Question 12 1pts
Prior to creating a network, it is important to:
Group of answer choices
Identify the party responsible for each activity.
Calculate the float for each activity.
Identify all loops through activities.
Understand the activity precedence.
Flag question: Question 13
Question 13 1pts
The critical path method calculates the theoretical early start and finish dates. The difference between the late start and early start of a task is called :
Group of answer choices
Feeding buffer
Total float
Free float
Danger zone
Flag question: Question 14
Question 14 1pts
The least amount of float (total slack) is found:
Group of answer choices
After a burst activity.
In a resource-limited schedule.
After a merge activity.
On the critical path.
Flag question: Question 15
Question 15 1pts
The technique most commonly used by project management software packages to construct a project schedule network diagram is:
Group of answer choices
Activity on Node (AON)
Node On Activity (NOA)
Activity In Node (AIN)
Finish to Start
Flag question: Question 16
Question 16 1pts
There are two activities on your schedule: 1) Install server in lab; 2) However, the second task cannot start until the server has run in the lab for five days without failure. This is an example of what?
Group of answer choices
Fast Track
Crashing
Lead
Lag
Flag question: Question 17
Question 17 1pts
To control the schedule, a project manager is reanalyzing the project to predict project duration. This is done by analyzing the sequence of activities with the least amount of flexibility. What technique is being used?
Group of answer choices
Flowchart
Leads and Lags
Work Breakdown Structure
Critical path method
Flag question: Question 18
Question 18 1pts
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?
Activity | Time | Predecessor |
A | 5 | -- |
B | 7 | -- |
C | 8 | A |
D | 7 | A |
E | 4 | B |
F | 8 | C, D |
G | 9 | E, F |
H | 7 | G |
Group of answer choices
14
12
13
11
Flag question: Question 19
Question 19 1pts
What is the total slack time for Activity B given the activity times and precedence requirements shown in the table?
Activity | Time | Predecessor |
A | 5 | -- |
B | 7 | -- |
C | 8 | A |
D | 7 | A |
E | 4 | B |
F | 8 | C, D |
G | 9 | E, F |
H | 7 | G |
Group of answer choices
8
10
7
9
Flag question: Question 20
Question 20 1pts
Which of the following is correct?
Group of answer choices
A project can never have negative float.
The critical path helps prove how long the project will take.
The network diagram will change every time the end date changes.
There can be only one critical path.
Flag question: Question 21
Question 21 1pts
Which of the following is generally the most correct use of a project network diagram?
Group of answer choices
Defining the project costs.
Documenting activity interdependencies
Defining project resources
Showing the project schedule
Flag question: Question 22
Question 22 1pts
Which of the following is the best project management tool to use to determine the longest time the project will take?
Group of answer choices
Project Charter
Bar Chart
Network diagram
WBS
Flag question: Question 23
Question 23 1pts
Which of these precedence relationships is most commonly used in the Precedence Diagramming Method?
Group of answer choices
Start to Finish
Start to Start
Finish to start
Finish to Finish
Flag question: Question 24
Question 24 1pts
While developing the project schedule, you will find that the completion of successor activity depends on the completion of its predecessor activuity. What is the dependency called?
Group of answer choices
Start to Start
Finish to Finish
Start to Finish
Finish to Start
Flag question: Question 25
Question 251pts
You have been assigned a project where you are responsible for building a condo complex in a resort town. The project is expected to take two years to complete. During your work break structure meeting, you have decomposed many deliverables into work packages and schedule activities. However, there are some work packages that will be occuring a year from now, so you have elected not decomposed those deliverables and work packages at this time. This technique is called as :
Group of answer choices
Time delayed decomposition
Scope creep
Rolling wave planning
Poor planning
Flag question: Question 26
Question 26 1pts
You have a project with four activities as follows. Activity 1 can start immediately and has an estimated durtion of 1. Activity 2 can start after activity 1 and has an estimated duration of 4. Activity 3 can start after activity 2 is completed and has an estimated duration of 5. Activity 4 has an estimated duration of 8. It can start after activity 1 is completed. Both activity 3 and activity 4 must be completed before the project is complete. What is the critical path of the project?
Group of answer choices
Start, 1, 4, 3, End
Start, 1, 2, 3, End
Start, 1, 4, End
Start, 1, 2, 3, 4, End
Flag question: Question 27
Question 27 1pts
You are managing a project that involves work on a film shoot. The editing activity can happen only after the film has been shot. The logical relationship between the editing and shooting of the film can best be described as:
Group of answer choices
Finish to finish
Finish to start
Start to start
Start to finish
PLEASE HELP TO ANSWER THIS AND BOLD THE ANSWER
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started