QUIZ 1: SCHEDULE MANAGEMENT Question 1 1pts A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has

QUIZ 1: SCHEDULE MANAGEMENT

Question 1 1pts

A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the late finish for the Plant Posts activity?

Activity

Optimistic time

Most Likely time

Pessimistic time

Predecessor

Corner Posts

4

5

6

--

String Line

7

8

9

--

Dig Holes

10

12

14

Corner Posts

Plant Posts

11

14

17

String Line

Weld Top Bar

8

11

14

String Line

Paint

9

11

13

Dig Holes, Plant Posts

Tack Wire

9

12

16

Weld Top Bar

Group of answer choices

13.3 days

8 days

20.83 days

22 days

Flag question: Question 2

Question 2 1pts

A project has three critical paths. Which of the following best describes how this affects the project?

Group of answer choices

It makes it more expensive

It makes it easier to manage

It increases the project risk

It requires more people

Flag question: Question 3

Question 3 1pts

An activity has an early start of day 3, a late start of day 13, an early finish of day 9, and a late finish of day 19. The activity:

Group of answer choices

Is on the critical path

Has a lag

Is progressing well

It is not on the critical path

Flag question: Question 4

Question 4 1pts

At a burst point in a backward pass, the largest succeeding late start becomes the late finish for that node.

Group of answer choices

True

False

Flag question: Question 5

Question 5 1pts

At a merge point in a forward pass, the largest preceding early finish becomes the early start for that node.

Group of answer choices

True

False

Flag question: Question 6

Question 6 1pts

Based on the activity network pictured, what is the BEST statement?

Group of answer choices

Before starting Activity C, Activity A and Activity B must be completed.

Before starting Activity C, Activity A and Activity D must be completed.

Before starting Activity E, Activity A and Activity B need to be completed.

Before starting Activity D, Activity A and Activity B need to be completed.

Flag question: Question 7

Question 7 1pts

Calculation of late finish dates and late start dates for the uncompleted portion of the project is called ________________

Group of answer choices

Schedule compression

A backward pass

A forward pass

An arrow diagram

Flag question: Question 8

Question 8 1pts

In a finish-to-start relationship between predecessor and successor activities, a project manager decides to schedule a successor activity five days before its predecessor is complete. This is accomplished by providing five days of:

Group of answer choices

Load

Fast tracking

Lag

Lead

Flag question: Question 9

Question 9 1pts

In a project, activity A has a duration of 4 days and begins on the morning of Monday the 4th. The successor activity, B, has a Finish-to-Start (FS) relationship with A. The Finish-to start relationship has a 2 days of lag. Activity B has a duration of 3 days. If Saturday and Sunday are non-working days, which of the following statements s true?

Group of answer choices

Activity B will be completed by end of the day on Thursday, 14th.

Activity B will be completed by end of the day on Tuesday, 12th.

Activity B will be completed by end of the day on Friday, 15th.

Activity B will be completed by end of the day on Wednesday, 13th.

Flag question: Question 10

Question 10 1pts

Lag means

Group of answer choices

The amount of time an activity can be delayed without delaying the early start date of its successor.

The amount of time an activity can be delayed without delaying the project finish date.

Waiting time

The product of a forward and backward pass.

Flag question: Question 11

Question 11 1pts

Most project management software packages use a method of constructing a project schedule network diagram known as:

Group of answer choices

Precedence Diagramming Method

Project Diagramming Method

Activity Diagramming Method

Critical Diagramming Method

Flag question: Question 12

Question 12 1pts

Prior to creating a network, it is important to:

Group of answer choices

Identify the party responsible for each activity.

Calculate the float for each activity.

Identify all loops through activities.

Understand the activity precedence.

Flag question: Question 13

Question 13 1pts

The critical path method calculates the theoretical early start and finish dates. The difference between the late start and early start of a task is called :

Group of answer choices

Feeding buffer

Total float

Free float

Danger zone

Flag question: Question 14

Question 14 1pts

The least amount of float (total slack) is found:

Group of answer choices

After a burst activity.

In a resource-limited schedule.

After a merge activity.

On the critical path.

Flag question: Question 15

Question 15 1pts

The technique most commonly used by project management software packages to construct a project schedule network diagram is:

Group of answer choices

Activity on Node (AON)

Node On Activity (NOA)

Activity In Node (AIN)

Finish to Start

Flag question: Question 16

Question 16 1pts

There are two activities on your schedule: 1) Install server in lab; 2) However, the second task cannot start until the server has run in the lab for five days without failure. This is an example of what?

Group of answer choices

Fast Track

Crashing

Lead

Lag

Flag question: Question 17

Question 17 1pts

To control the schedule, a project manager is reanalyzing the project to predict project duration. This is done by analyzing the sequence of activities with the least amount of flexibility. What technique is being used?

Group of answer choices

Flowchart

Leads and Lags

Work Breakdown Structure

Critical path method

Flag question: Question 18

Question 18 1pts

What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?

Activity

Time

Predecessor

A

5

--

B

7

--

C

8

A

D

7

A

E

4

B

F

8

C, D

G

9

E, F

H

7

G

Group of answer choices

14

12

13

11

Flag question: Question 19

Question 19 1pts

What is the total slack time for Activity B given the activity times and precedence requirements shown in the table?

Activity

Time

Predecessor

A

5

--

B

7

--

C

8

A

D

7

A

E

4

B

F

8

C, D

G

9

E, F

H

7

G

Group of answer choices

8

10

7

9

Flag question: Question 20

Question 20 1pts

Which of the following is correct?

Group of answer choices

A project can never have negative float.

The critical path helps prove how long the project will take.

The network diagram will change every time the end date changes.

There can be only one critical path.

Flag question: Question 21

Question 21 1pts

Which of the following is generally the most correct use of a project network diagram?

Group of answer choices

Defining the project costs.

Documenting activity interdependencies

Defining project resources

Showing the project schedule

Flag question: Question 22

Question 22 1pts

Which of the following is the best project management tool to use to determine the longest time the project will take?

Group of answer choices

Project Charter

Bar Chart

Network diagram

WBS

Flag question: Question 23

Question 23 1pts

Which of these precedence relationships is most commonly used in the Precedence Diagramming Method?

Group of answer choices

Start to Finish

Start to Start

Finish to start

Finish to Finish

Flag question: Question 24

Question 24 1pts

While developing the project schedule, you will find that the completion of successor activity depends on the completion of its predecessor activuity. What is the dependency called?

Group of answer choices

Start to Start

Finish to Finish

Start to Finish

Finish to Start

Flag question: Question 25

Question 251pts

You have been assigned a project where you are responsible for building a condo complex in a resort town. The project is expected to take two years to complete. During your work break structure meeting, you have decomposed many deliverables into work packages and schedule activities. However, there are some work packages that will be occuring a year from now, so you have elected not decomposed those deliverables and work packages at this time. This technique is called as :

Group of answer choices

Time delayed decomposition

Scope creep

Rolling wave planning

Poor planning

Flag question: Question 26

Question 26 1pts

You have a project with four activities as follows. Activity 1 can start immediately and has an estimated durtion of 1. Activity 2 can start after activity 1 and has an estimated duration of 4. Activity 3 can start after activity 2 is completed and has an estimated duration of 5. Activity 4 has an estimated duration of 8. It can start after activity 1 is completed. Both activity 3 and activity 4 must be completed before the project is complete. What is the critical path of the project?

Group of answer choices

Start, 1, 4, 3, End

Start, 1, 2, 3, End

Start, 1, 4, End

Start, 1, 2, 3, 4, End

Flag question: Question 27

Question 27 1pts

You are managing a project that involves work on a film shoot. The editing activity can happen only after the film has been shot. The logical relationship between the editing and shooting of the film can best be described as:

Group of answer choices

Finish to finish

Finish to start

Start to start

Start to finish

PLEASE HELP TO ANSWER THIS AND BOLD THE ANSWER

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Small Business Management Launching And Growing Entrepreneurial Ventures

Authors: Justin G. Longenecker, J. William Petty, Leslie E. Palich, Frank Hoy

19th Edition

0357039416, 9780357039410

More Books

Students also viewed these General Management questions