Question

1 Approved Answer

Refer to Figure 4 . Which is not true about the PERT schedule? Select the most appropriate one. Figure 4 Activity x = optimistic duration

Refer to Figure 4. Which is not true about the PERT schedule? Select the most appropriate one.
Figure 4
Activity
x= optimistic duration
(x,y,z)
y= most-likely duration
z= pessimistic duration
(A) The standard deviation for Activity C's duration is 13.
B Activity B has the longest expected duration among the four activities.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions