While resource planning for your project, you visited the functional manager of engineering many times but she refused to supply resources for the project. First,
While resource planning for your project, you visited the functional manager of engineering many times but she refused to supply resources for the project. First, the excuse was that her department was too busy. The next time, the department was undergoing reorganization. This is causing your project to slip the schedule. The lack of which of the following is the MOST probable reason for her lack of support?