Refer to the network below Baseline schedule PS Activity 0,6 J 0,6 0,2 B 2 1,3...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Refer to the network below Baseline schedule PS Activity 0,6 J 0,6 0,2 B 2 1,3 0,9 C g ABCDEFGH 1629475108 11, 20 Duration 32 IPA A. B B D D. E 6,10 C. F. G A 6, 10 15, 20 10, 20 28, 30 hg0 m 10 10, 20 28, 30 2,9 E 7 3,10 CE0006210 10 20 ES EF 6 2 9 10 9 15 20 28 C, G 20 23 HT 28 10, 15 F 30 LS 1 TO- 1635 10 20 |U6320 10 10 20 20 28 28 30 -101500 1500 25 28 11 20, 28 LF H 20, 28 20, 23 1 3 25, 28 TF 1 po FF FO 0 5o Fifteen days after the start of the project, the following information is received. - Activity A Completed 2 days later than planned - Activity B Completed on time - Activity C Started; 4 days left - Activity D Completed; took 5 days to finish - Activity E Completed - Activity F Canceled - Activity G Started 3 days late; project manager hopes to cut 1 day of its duration - Activity K Added: Duration = 4 days. IPA - C - Activity LAdded: Duration=3 days. IPA - K, G - Activity | Adjusted: IPA - L Draw the updated network. Calculate the new project completion date. Check if there are changes to the completion date and/or to the critical path. Mention the causes for such changes, if any. Refer to the network below Baseline schedule PS Activity 0,6 J 0,6 0,2 B 2 1,3 0,9 C g ABCDEFGH 1629475108 11, 20 Duration 32 IPA A. B B D D. E 6,10 C. F. G A 6, 10 15, 20 10, 20 28, 30 hg0 m 10 10, 20 28, 30 2,9 E 7 3,10 CE0006210 10 20 ES EF 6 2 9 10 9 15 20 28 C, G 20 23 HT 28 10, 15 F 30 LS 1 TO- 1635 10 20 |U6320 10 10 20 20 28 28 30 -101500 1500 25 28 11 20, 28 LF H 20, 28 20, 23 1 3 25, 28 TF 1 po FF FO 0 5o Fifteen days after the start of the project, the following information is received. - Activity A Completed 2 days later than planned - Activity B Completed on time - Activity C Started; 4 days left - Activity D Completed; took 5 days to finish - Activity E Completed - Activity F Canceled - Activity G Started 3 days late; project manager hopes to cut 1 day of its duration - Activity K Added: Duration = 4 days. IPA - C - Activity LAdded: Duration=3 days. IPA - K, G - Activity | Adjusted: IPA - L Draw the updated network. Calculate the new project completion date. Check if there are changes to the completion date and/or to the critical path. Mention the causes for such changes, if any.
Expert Answer:
Answer rating: 100% (QA)
Given the updates to the project we need to adjust the network diagram and recalculate the project completion date Since I cannot physically draw the ... View the full answer
Related Book For
Posted Date:
Students also viewed these general management questions
-
Calculate the first 2 years of depreciation under each of the following methods. Historical Cost Salvage Value $60,000 $ 5,000 Useful Life 10 years A) Straight Line B) Double Declining Balance Sum of...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-5. Ivan's grandfather died and left a portfolio of municipal bonds. In 2012, they pay Ivan...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-6. On December 12, Irene purchased the building where her store is located. She paid...
-
Think about the impact that e-commerce and more flexible networks of organisations has had on the way international business is conducted. How has it created new complexities in the relationships...
-
Let β1DM denote the entity-demeaned estimator given in Equation (10.22), and let β1BA denote the "before and after" estimator without an intercept, so that Show that, if and...
-
A manager of Paris Manufacturing that produces computer hard drives is planning to lease a new automated inspection system. The manager believes the new system will be more accurate than the current...
-
Effect of transactions on ratios (Learning Objective 4) Financial statement data on 170 RV Park include the following: Requirements 1. Compute 170 RV Parks current ratio, debt ratio, and earnings per...
-
Manual Company sells goods to Nolan Company during 2012. It offers Nolan the following rebates based on total sales to Nolan. If total sales to Nolan are 10,000 units, it will grant a rebate of 2%....
-
Find the Riemann sum of: a) f(x)= x^2+2 over the interval (8,4) by using 4 sub-intervals evaluated at the right endpoint. b)f(x)=1/1+x^5 over the interval (0,2) by using the left endpoint rule with...
-
Ryan Ross (111-11-1112), Oscar Omega (222-22-2223), Clark Carey (333-33-3334), and Kim Kardigan (444-44-4445) are equal active members in ROCK the Ages LLC. ROCK serves as agent and manager for...
-
1. An overview of an organization of your choice briefly describe the nature of the organization including its history, products/services, size, and competition. 2. An explanation of competitive...
-
Costco Costco is one of the largest retail sales companies in the United States, and it has more than 500 stores in 37 states and eight countries. Despite low profit margins in the retailing...
-
Campbell Limited is a manufacturer of telecommunication switches. The company uses job order costing to assign costs to its product. During 2019, Campbell manufactured a Switch for Eastlink...
-
How modern managerial accounting practices help companies grow Companies can find new ways to grow through forward-looking managerial accounting approaches. Improving business performance and...
-
A consol bond pays forever two semiannual coupons at an annual coupon rate of 3.60% In other words, the initial principal is never reduced nor repaid.The yield-to-maturity is 6.80% and a coupon was...
-
Question 1 a. Define property, plant and equipment and identify the four primary issues in accounting for them. (5 marks) b. On 1 January 2020, Berjaya Berhad bought a machine for RM95,200 on credit...
-
Sheridan Company had sales in 2022 of $1,457,500 on 58,300 units. Variable costs totalled $583,000, and fixed costs totalled $730,300. A new raw material is available that will decrease the variable...
-
How do network effects help Facebook fend off smaller social-networking rivals? Could an online retailer doing half as much business compete on an equal footing with Amazon in terms of costs? Explain.
-
Wet concrete exerts a pressure distribution along the wall of the form. Determine resultant force of this distribution and specify the height h where the bracing strut should be placed so that it...
-
Determine the normal force, shear force, and moment at points D of the two-member frame. 2 kN/m A -1.5 m D -1.5 m 1.5 m E 1.5 m O F B 1.5 kN/m
-
Determine the location (x, ) of the centroid of the sheet metal cross section. Neglect the thickness of the material and slight bends at the corners. y 2 in. 8 in. -3 in.3 in. X
-
Effects of FIFO and Weighted Average} Sheepskin Company sells to colleges and universities a special paper that is used for diplomas. Sheepskin typically makes one purchase of the special paper each...
-
Examine the cash flow measures in requirement 2 of the review problem in this chapter. Discuss the meaning of these ratios. Computing Cash Flows from Operating Activities: Indirect Method
-
During 20x7, Arizona Company issued $500,000 in long-term bonds at 96, repaid $75,000 of bonds at face value, paid interest of $40,000, and paid dividends of $25,000. Prepare the cash flows from the...
Study smarter with the SolutionInn App