requirement: calculate the total variable costs of producing 2, 4, 8 units. begin by calculating the total cumulative time in labor hours. (round the cumalitive
requirement:
Data Table 9/5/2021 S 85,000 per unit of RS-32 3,900 direct manufacturing labor hours 85% cumulative average time" 29 per direct manufacturing labor-hour 14 per direct manufacturing labor-hout Direct material cost Direct manufacturing labor time for first unit Learning curve for manufacturing labor time per radar system Direct manufacturing labor cost Variable manufacturing overhead cost In 0.85 -0.162519 Using the formula for an 85% learning curve, b = In 2 0.693147 $ $ -0.234465 X=2; 4 = 3900x24-0.234465) x=4, y=3900 41 x=8j X= y = 3900 81 3900 x 85= 3315 3315 *.85=2818 2818 8.85-2395 3900+3315=7215 12152818 = 10033 6033+ 2395=12428 2818 12395.088763 calculate the total variable costs of producing 2, 4, 8 units.
begin by calculating the total cumulative time in labor hours. (round the cumalitive avg time per unit to the nearest whole number)
{i have my work below, please let me know what i am doing wrong}
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started