Right before a project is about to start construction, the customer changes their mind and wants to add additional work. Which of the following

  

Right before a project is about to start construction, the customer changes their mind and wants to add additional work. Which of the following actions should the Project Manager do FIRST? Determine the impact upon the project critical path O Discuss the potential impact with the Project Sponsor and prepare to defend the delay to Senior Management Meet with customer to persuade them to cancel the additional work Meet with the customer to understand the additional work

Step by Step Solution

3.46 Rating (149 Votes )

There are 3 Steps involved in it

Step: 1

Meet with the customer to understand the additional wo... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Financial Management

Authors: Eugene F. Brigham, Joel F. Houston

10th edition

978-1337902571, 1337902578, 978-1337911054, 1337911054, 978-0324272055

More Books

Students also viewed these General Management questions

Question

Given find the value of k. es 1 e kx dx = 1 4'

Answered: 1 week ago