Risk management should be incorporated into every project in order to absorb, minimize, or eliminate events that could impact your budget and timeline. As stated

Risk management should be incorporated into every project in order to absorb, minimize, or eliminate events that could impact your budget and timeline. As stated in the PMBOK, the purpose of risk monitoring is to determine whether 


a. Risk responses have been implemented as planned 


b. Project assumptions are still valid


c. A risk trigger has occurred


d. All of the above



Step by Step Solution

There are 3 Steps involved in it

Step: 1

The detailed answer for the above question is provided below Answer d All of the above Explanation lets delve into each aspect mentioned in the contex... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield.

9th Canadian Edition, Volume 2

470964731, 978-0470964736, 978-0470161012

More Books

Students also viewed these General Management questions