Question

1 Approved Answer

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) ABCDEFG This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = days. d) Slack time for each of the activities is: B A, D E, F Activity A B C DEFG Time (days) 3 6 Slack Time 383580 10
image text in transcribed
pls help me !! its urgent
This erorche contsins only parts b, C, and d b) The crical activites for the leadenhip training program development project are c) The project length foc the leadership iraining program development project * day. d) Sinck time for each of the activites is

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Fundamentals Of Fashion Management

Authors: Susan Dillon

2nd Edition

1474271219, 978-1474271219

More Books

Students also viewed these General Management questions

Question

Identify the methods of valuing an equity security.

Answered: 1 week ago

Question

Presentation Aids Practicing Your Speech?

Answered: 1 week ago