Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time ( weeks
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.
Time weeks
Immediate
Time weeks
Immediate
Activity
a
m
b
Predecessors
Activity
a
m
b
Predecessors
A
long dash
G
C E
B
A
H
F
C
A
I
F
D
A
J
D G H
E
B
K
I J
F
C E
Part
a The expectedestimated time for activity C is
enter your response here weeks. Round your response to two decimal places.
Part
b The variance for activity C is
enter your response here weeks. Round your response to two decimal places.
Part
c Based on the calculation of the estimated times, the critical path is
A C F I K
A D J K
A B E G J K
A B E F I K
A B E F H J K
A C G J K
A C F H J K
Part
d The estimated time for the critical path is
enter your response here weeks. Round your response to two decimal places.
Part
e The activity variance along the critical path is
enter your response here weeks. Round your response to two decimal places.
Part
f Using the standard normal tableLOADING... the probability that Hopkins Hospitality will finish the project in weeks or less is
enter your response here. Enter as a probability and round your response to three decimal places.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started