Ruby s project metrics says that her project has for SPI of . 8 3 and CPI of 1 . 3 . How cans Ruby
Rubys project metrics says that her project has for SPI of and CPI of How cans Rubys Project status be BEST described?
Question Select one:
a
Project is behind schedule and over budget
b
Project is behind schedule and under budget
c
Project is ahead of schedule and over budget
d
Project is ahead of schedule and under budget