Sandhill Construction Company uses the percentage-of-completion method of accounting. In 2020, Sandhill began work under a non-cancellable contract #E2-D2, which provided for a contract price

Sandhill Construction Company uses the percentage-of-completion method of accounting. In 2020, Sandhill began work under a non-cancellable contract #E2-D2, which provided for a contract price of $2,159,000. Other details follow:



2020
2021
Costs incurred during the year


$571,320
$1,446,000
Estimated costs to complete, as at December 31


1,015,680
0
Billings during the year (non-refundable)


415,000
1,545,600
Collections during the year


349,000
1,505,000


(A) 

How much revenue should be recognized in 2020 and in 2021?




2020
2021
Revenue to be recognized

$enter a dollar amount
$enter a dollar amount


(B) 

Assuming the same facts as those above except that Sandhill uses the completed-contract method of accounting, how much revenue should be recognized in 2021?




2021
Revenue to be recognized

$enter a dollar amount

(C) 

Prepare a complete set of journal entries for 2020. (using the percentage-of-completion method. Use Materials, Cash, Payables for costs incurred to date.) (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

Account Titles and Explanation
Debit
Credit



enter an account title to record cost of construction
enter a debit amount
enter a credit amount
(To record cost of construction)





enter an account title to record progress billings
enter a debit amount
enter a credit amount
(To record progress billings)





enter an account title to record collections
enter a debit amount
enter a credit amount
(To record collections)





enter an account title to record revenues
enter a debit amount
enter a credit amount
(To record revenues)





enter an account title to record construction expenses
enter a debit amount
enter a credit amount
(To record construction expenses)

Step by Step Solution

3.56 Rating (156 Votes )

There are 3 Steps involved in it

Step: 1

a 2020 2021 a Contract price 2159000 2159000 b Cost incurred to date ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Ray H. Garrison, Eric W. Noreen, Peter C. Brewer

13th Edition

978-0073379616, 73379611, 978-0697789938

More Books

Students also viewed these Accounting questions

Question

How can sensitivity to pain be altered?

Answered: 1 week ago

Question

What is the cerebrum?

Answered: 1 week ago