Question

1 Approved Answer

Scenario 1: Crown Construction Company entered into a contract with Star Hotel for building a highly sophisticated customized conference room to be completed for a

image text in transcribed

Scenario 1: Crown Construction Company entered into a contract with Star Hotel for building a highly sophisticated customized conference room to be completed for a fixed price of $400,000. Nonrefundable progress payments are made on a monthly basis for work completed during the month. Legal title to the conference room equipment is held by Crown until the end of the construction project, but if the contract is terminated before the conference room is finished, Star retains the partially completed job and must pay for any work completed to date Scenario 2: Regent Company entered into a contract with Star Hotel for constructing and installing a standard designed gym for a fixed price of $400,000. Nonrefundable progress payments are made on a monthly basis for work completed during the month. Legal title to the gym passes to Star upon completion of the building process. If Star cancels the contract before the gym construction is completed, Regent removes all the installed equipment and Star must compensate Regent for any loss of profit on sale of the gym to another customer. Scenario 3: On January 1, the CostDriver Company, a consulting firm, entered into a three-month contract with Coco Seafood Restaurant to analyze its cost structure in order to find a way to reduce operating costs and increase profits CostDriver promises to share findings with the restaurant every two weeks and to provide the restaurant with a final analytical report at the end of the contract. This service is customized to Coco, and CostDriver would need to start from scratch if it provided a similar service to another client. Coco promises to pay $5,000 per month. If Coco cho0ses to terminate the contract, it is entitled to receive a report detailing analyses to that stage. Scenario 4: Assume Trump International Tower (Phase II) is developing luxury residential real estate and begins to market individual apartments during their construction. The Tower entered into a contract with Edwards for the sale of specific apartment. Edwards pays a deposit that is refundable only if the Tower fails to deliver the completed apartment in accordance with the contract. The remainder of the purchase price is paid on completion of the contract when Edwards obtains possession of the apartment Required: Page 290 For each of the scenarios, determine whether the seller should recognize revenue (a) over time or (b) when the product or service is completed. Explain your answer Scenario 1: Crown Construction Company entered into a contract with Star Hotel for building a highly sophisticated customized conference room to be completed for a fixed price of $400,000. Nonrefundable progress payments are made on a monthly basis for work completed during the month. Legal title to the conference room equipment is held by Crown until the end of the construction project, but if the contract is terminated before the conference room is finished, Star retains the partially completed job and must pay for any work completed to date Scenario 2: Regent Company entered into a contract with Star Hotel for constructing and installing a standard designed gym for a fixed price of $400,000. Nonrefundable progress payments are made on a monthly basis for work completed during the month. Legal title to the gym passes to Star upon completion of the building process. If Star cancels the contract before the gym construction is completed, Regent removes all the installed equipment and Star must compensate Regent for any loss of profit on sale of the gym to another customer. Scenario 3: On January 1, the CostDriver Company, a consulting firm, entered into a three-month contract with Coco Seafood Restaurant to analyze its cost structure in order to find a way to reduce operating costs and increase profits CostDriver promises to share findings with the restaurant every two weeks and to provide the restaurant with a final analytical report at the end of the contract. This service is customized to Coco, and CostDriver would need to start from scratch if it provided a similar service to another client. Coco promises to pay $5,000 per month. If Coco cho0ses to terminate the contract, it is entitled to receive a report detailing analyses to that stage. Scenario 4: Assume Trump International Tower (Phase II) is developing luxury residential real estate and begins to market individual apartments during their construction. The Tower entered into a contract with Edwards for the sale of specific apartment. Edwards pays a deposit that is refundable only if the Tower fails to deliver the completed apartment in accordance with the contract. The remainder of the purchase price is paid on completion of the contract when Edwards obtains possession of the apartment Required: Page 290 For each of the scenarios, determine whether the seller should recognize revenue (a) over time or (b) when the product or service is completed. Explain your

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective Auditing The Simple Systems Series Book 5

Authors: Jennie Clark CQP

1st Edition

B09YHJR18Y, 979-8802614082

More Books

Students also viewed these Accounting questions

Question

6. Explain the strengths of a dialectical approach.

Answered: 1 week ago

Question

2. Discuss the types of messages that are communicated nonverbally.

Answered: 1 week ago