Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes

Scenario Analysis

Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis:

Economic Scenario Probability of Outcome NPV
Recession 0.05 -$52 million
Below average 0.20 -16 million
Average 0.50 12 million
Above average 0.20 14 million
Boom 0.05 40 million

What are the project's expected NPV, standard deviation, and coefficient of variation? Enter your answers for the NPV and standard deviation in millions. For example, an answer of $1.24 million should be entered as 1.24, not 1,240,000. Do not round intermediate calculations. Round your answers to two decimal places.

E(NPV): $ million
NPV: $ million
CVNPV:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Futures And Options Markets

Authors: John Hull

9th Global Edition

1292422114, 9781292422114

More Books

Students also viewed these Finance questions