Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.
Job | Work Center/Machine Hours | Due Date (days) |
1 | A/3, B/2, C/2 | 3 |
2 | C/2, A/4 | 2 |
3 | B/6, A/1, C/3 | 4 |
4 | C/4, A/1, B/2 | 3 |
- What is the makespan?
- How much machine idle time is there?
- When is each job delivered compared with its due date?
- How much idle time (waiting time) is there for each job?
- Devise a better job sequence for processing
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started