Sequencing jobs through two work centres/machines. Use Johnsonss rule to obtain: a) The sequence that minimizes the make-span for the jobs shown below through work
Sequencing jobs through two work centres/machines. Use Johnsonss rule to obtain: a) The sequence that minimizes the make-span for the jobs shown below through work centre 1 and 2. b) Find make-span Job Work centre 1 Work centre 2 a 2.5 4.2 b 3.8 1.5 c 2.2 3 d 5.8 4 e 4.5 2