Question
1 Approved Answer
Shawn's Shoes is trying to improve their operations by optimizing the number of machines. The longest task takes 2.6minutes to complete, and the total time
Shawn's Shoes is trying to improve their operations by optimizing the number of machines.
The longest task takes 2.6minutes to complete, and the total time for all tasks is 9.6minutes.This product line operates 470 minutes per day.
How many machines are needed if Shawn wants 1290 shoes to be produced each day?