Question
1 Approved Answer
Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A
Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Ball bearings Order Policy: 500 units. Lead Time: 1 week Quantity Week on Hand: 400 1 4 5 6 7 8 9 10 Forecast 550 350 400 400 350 300 150 300 400 450 Customer orders 300 350 250 250 200 100 50 50 100 150 150 (booked) Projected on-hand inventory MPS quantity 500