Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $119,520. Overhead is
Single plantwide factory overhead rate
Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $119,520. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit:
Budgeted Production VolumeDirect Labor Hours Per Unit
Flutes1,800units0.6
Clarinets500 1.6
Oboes1,200 1.2
If required, round all per unit answers to the nearest cent.
a. Determine the single plantwide overhead rate.
$fill in the blank 1
per direct labor hour
b. Use the overhead rate in (a) to determine the amount of total and per-unit overhead allocated to each of the three products.
Total
Factory Overhead CostPer Unit
Factory Overhead Cost
Flutes$fill in the blank 2
$fill in the blank 3
Clarinets fill in the blank 4
fill in the blank 5
Oboes fill in the blank 6
fill in the blank 7
Total $fill in the blank 8
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started