SleepSoft is a manufacturer of high-end pillows. Their process involves five activities which are carried out in a particular order. Their pillows have a demand
SleepSoft is a manufacturer of high-end pillows. Their process involves five activities which are carried out in a particular order. Their pillows have a demand of 12 units per hour. The processing time, the number of workers, and the capacity are given in the table below for each activity. Note: One worker performs both stuffing and embroidering.
Activity | Prorcessing Time (minutes/unit) | # of Workers |
Cutting | 4 | 2 |
Serwing | 8 | 3 |
Stuffing & Embroidering | 4 | 1 |
Packaging | 2 | 1 |
What is the flow rate of the process in units per hour and which activity is the bottneck?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started