Question
Southside Pizzeria wants to improve its ability to manage the ingredient costs associated with making and selling its pizzas. For the month of June, the
Southside Pizzeria wants to improve its ability to manage the ingredient costs associated with making and selling its pizzas. For the month of June, the company plans to make 1,000 pizzas. It has created a planning budget that includes a cost formula for mozzarella cheese of $9.20 per pizza. At the end of June, Southside actually sold 1,100 pizzas and the actual cost of the cheese that it used during the month was $2,914.
Required:
1. What is the mozzarella cheese spending variance for June?
2. Assume that the company establishes a price standard of $1.15 per ounce for mozzarella cheese and a quantity standard of eight ounces of cheese per pizza. Also, assume that Southside actually used 9,400 ounces of cheese during the month to make 1,100 pizzas.
(Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
a. What is the materials price variance for mozzarella cheese for June?
b. What is the materials quantity variance for mozzarella cheese for June?
c. What is the materials spending variance for mozzarella cheese for June?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started