Question
Standard Actual Material Cost Per Yard $2.00 $2.10 Standard Yards per Unit 4.5 yards 4.75 yards Units of Production 9,500 5. Calculate the Total Direct
| Standard | Actual |
Material Cost Per Yard | $2.00 | $2.10 |
Standard Yards per Unit | 4.5 yards | 4.75 yards |
Units of Production |
| 9,500 |
5. Calculate the Total Direct Materials cost variance using the above information:
a. | $9,262.50 Unfavorable |
b. | $9,262.50 Favorable |
c. | $3,780.00 Unfavorable |
d. | $3,562.50 Favorable |
6. Calculate the Direct Materials Price variance using the above information:
a. | $1,795.50 Favorable |
b. | $378.00 Favorable |
c. | $4,512.50 Unfavorable |
d. | $378.00 Unfavorable |
7. Calculate the Direct Materials Quantity variance using the above information:
a. | $4,512.50 Unfavorable |
b. | $4,512.50 Favorable |
c. | $4,750 Unfavorable |
d. | $4,750 Favorable |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started