Question

1 Approved Answer

Standard Actual Material Cost Per Yard $2.00 $2.10 Standard Yards per Unit 4.5 yards 4.75 yards Units of Production 9,500 5. Calculate the Total Direct

Standard

Actual

Material Cost Per Yard

$2.00

$2.10

Standard Yards per Unit

4.5 yards

4.75 yards

Units of Production

9,500

5. Calculate the Total Direct Materials cost variance using the above information:

a.

$9,262.50 Unfavorable

b.

$9,262.50 Favorable

c.

$3,780.00 Unfavorable

d.

$3,562.50 Favorable

6. Calculate the Direct Materials Price variance using the above information:

a.

$1,795.50 Favorable

b.

$378.00 Favorable

c.

$4,512.50 Unfavorable

d.

$378.00 Unfavorable

7. Calculate the Direct Materials Quantity variance using the above information:

a.

$4,512.50 Unfavorable

b.

$4,512.50 Favorable

c.

$4,750 Unfavorable

d.

$4,750 Favorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Custom Edition For University Of Central Florida From Managerial Accounting

Authors: Karen Wilken Braun, Wendy Tietz

3rd Edition

1269451839, 978-1269451833

More Books

Students also viewed these Accounting questions