Starshine products is considering the launch of a new line of dolls that would use an assembly line that currently has some spare capacity. Some
Starshine products is considering the launch of a new line of dolls that would use an assembly line that currently has some spare capacity. Some starshine executives argued that because the assembly line was already paid for, its cost was sunk and should not be included in the project evaluation. Other argued that the assembly line was a scarce resource and should be priced accordingly . what cost should sharshine assign to use of the excess assembly line capacity
select the correct answer
A- sunk cost
b-cannibilization
c- opportunity cost
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started