Strategy and Tactics in Project Management Assignment 7: Silver Zuma Project Part II Unit C. Todays date is Friday July 14, 2023 (Set baseline to

Strategy and Tactics in Project Management

Assignment 7: Silver Zuma Project Part II

Unit C.

Todays date is Friday July 14, 2023 (Set baseline to this date first). Table 1 summarizes the information regarding activities accomplished to date.

Table 1 Silver Zuma Project Update

Activity Start Date Finish Date % completed
Market analysis 01/09/23 02/10/23 100%
Product design 02/13/23 04/10/23 100%
Manufacturing study 03/15/23 05/14/23 100%
Product design selection 05/12/23 05/25/23 100%
Manufacturing process 07/24/23 0%
Detailed product design 05/19/23 80%
Test prototype 07/28/23 0%

Robin Lane has requested a written status report for the Zuma project.

Set the status date on 7/17/2023

Perform an earned value analysis. Where does the total project stands relative to budget?

(calculate PV, EV, AC, SV, CV, CPI, SPI, EAC, BAC, and VAC).

  1. How is the project progressing in terms of cost and schedule?
  2. Are any actions suggested by this information?
  3. Based on this information what will be the total estimated cost at completion?

Try to present the above information in a form worthy of consideration by top management.

Include a Tracking Gantt Chart with your report.

Note: Enter July 17th as the status report date since you are preparing your report on the July 20th.

  1. While preparing your report you receive a phone call from Jim Keltner, a fellow project manager. He is calling to see if one of the industrial engineers assigned to your project would be available to work on his project from August 10-14, 2023. What is your answer to his request?

Stop: Save your MPP work for Unit C, and resave it as Unit D and continue next section.

Unit D

Robin Lane has asked you to update completion and cost estimates for the Zuma project. Table 2 presents the revised estimates generated by the Zuma project team.

Based on this new information prepare a memo that answers the following questions:

Set the status date on 09/18/20, Friday.

Perform an earned value analysis. Where does the project stand relative to budget?

(calculate PV, EV, AC, SV, CV, CPI, SPI, EAC, BAC, and VAC).

5. How is the project progressing in terms of cost and schedule?

6. Are any actions suggested by this information?

7. Based on this information what will be the total estimated cost at completion?

Include a Tracking Gantt with a cost table for the estimated completion schedule.

Table 2 Silver Zuma Project Estimate to Completion

Activity Start Date Finish Date % completed
Market analysis 01/09/23 02/10/23 100%
Product design 02/13/23 04/10/23 100%
Manufacturing study 03/15/23 05/14/23 100%
Product design selection 05/12/23 05/25/23 100%
Detailed MRKT plan 09/07/23 09/25/23 100%
Manufacturing process 07/27/23 09/07/23 100%
Detailed product design 05/18/23 07/17/23 100%
Test prototype 07/24/23 08/26/23 100%
Finalized product design 09/02/23 70%
Order components 10/28/23 0%
Order production equip. 10/07/23 0%
Install production equip. 12/30/23 0%
Celebrate 02/02/23 0%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Tourism Supply Chain Management

Authors: Haiyan Song

1st Edition

0415581567, 9780415581561

More Books

Students also viewed these General Management questions