Strategy and Tactics in Project Management Assignment 7: Silver Zuma Project Part II Unit C. Todays date is Friday July 14, 2023 (Set baseline to
Strategy and Tactics in Project Management
Assignment 7: Silver Zuma Project Part II
Unit C.
Todays date is Friday July 14, 2023 (Set baseline to this date first). Table 1 summarizes the information regarding activities accomplished to date.
Table 1 Silver Zuma Project Update
Activity | Start Date | Finish Date | % completed |
Market analysis | 01/09/23 | 02/10/23 | 100% |
Product design | 02/13/23 | 04/10/23 | 100% |
Manufacturing study | 03/15/23 | 05/14/23 | 100% |
Product design selection | 05/12/23 | 05/25/23 | 100% |
Manufacturing process | 07/24/23 | 0% | |
Detailed product design | 05/19/23 | 80% | |
Test prototype | 07/28/23 | 0% |
Robin Lane has requested a written status report for the Zuma project.
Set the status date on 7/17/2023
Perform an earned value analysis. Where does the total project stands relative to budget?
(calculate PV, EV, AC, SV, CV, CPI, SPI, EAC, BAC, and VAC).
- How is the project progressing in terms of cost and schedule?
- Are any actions suggested by this information?
- Based on this information what will be the total estimated cost at completion?
Try to present the above information in a form worthy of consideration by top management.
Include a Tracking Gantt Chart with your report.
Note: Enter July 17th as the status report date since you are preparing your report on the July 20th.
- While preparing your report you receive a phone call from Jim Keltner, a fellow project manager. He is calling to see if one of the industrial engineers assigned to your project would be available to work on his project from August 10-14, 2023. What is your answer to his request?
Stop: Save your MPP work for Unit C, and resave it as Unit D and continue next section.
Unit D
Robin Lane has asked you to update completion and cost estimates for the Zuma project. Table 2 presents the revised estimates generated by the Zuma project team.
Based on this new information prepare a memo that answers the following questions:
Set the status date on 09/18/20, Friday.
Perform an earned value analysis. Where does the project stand relative to budget?
(calculate PV, EV, AC, SV, CV, CPI, SPI, EAC, BAC, and VAC).
5. How is the project progressing in terms of cost and schedule?
6. Are any actions suggested by this information?
7. Based on this information what will be the total estimated cost at completion?
Include a Tracking Gantt with a cost table for the estimated completion schedule.
Table 2 Silver Zuma Project Estimate to Completion
Activity | Start Date | Finish Date | % completed |
Market analysis | 01/09/23 | 02/10/23 | 100% |
Product design | 02/13/23 | 04/10/23 | 100% |
Manufacturing study | 03/15/23 | 05/14/23 | 100% |
Product design selection | 05/12/23 | 05/25/23 | 100% |
Detailed MRKT plan | 09/07/23 | 09/25/23 | 100% |
Manufacturing process | 07/27/23 | 09/07/23 | 100% |
Detailed product design | 05/18/23 | 07/17/23 | 100% |
Test prototype | 07/24/23 | 08/26/23 | 100% |
Finalized product design | 09/02/23 | 70% | |
Order components | 10/28/23 | 0% | |
Order production equip. | 10/07/23 | 0% | |
Install production equip. | 12/30/23 | 0% | |
Celebrate | 02/02/23 | 0% |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started