Sudhir is using the CPM estimating technique to estimate the duration of a particular activity. If the optimistic time is 20 hours, the most likely
Sudhir is using the CPM estimating technique to estimate the duration of a particular activity. If the optimistic time is 20 hours, the most likely time is 24 hours and the pessimistic time is 31 hours, what would be recorded for the length of time that the task will take? @ 25 hours 0 31 hours 0 24 hours 0 28 hours
Step by Step Solution
There are 3 Steps involved in it
Step: 1