Question
Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its
Sultan Company uses an activity-based costing system.
At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools:
Activity Cost Pool | Activity Measure | Expected Overhead Cost | Expected Activity | ||||
Labor-related | Direct labor-hours | $ | 400,000 |
| 40,000 |
| DLHs |
Purchase orders | Number of orders | $ | 11,150 |
| 223 |
| orders |
Parts management | Number of part types | $ | 82,820 |
| 101 |
| part types |
Board etching | Number of boards | $ | 73,800 |
| 1,640 |
| boards |
General factory | Machine-hours | $ | 279,500 |
| 21,500 |
| MHs |
Required:
1. Compute the activity rate for each of the activity cost pools.
2. The expected activity for the year was distributed among the companys four products as follows:
| Expected Activity | |||||||||||
Activity Cost Pool | Product A | Product B | Product C | Product D | ||||||||
Labor-related (DLHs) |
| 6,700 |
|
| 23,300 |
|
| 4,300 |
|
| 5,700 |
|
Purchase orders (orders) |
| 63 |
|
| 39 |
|
| 36 |
|
| 85 |
|
Parts management (part types) |
| 37 |
|
| 15 |
|
| 38 |
|
| 11 |
|
Board etching (boards) |
| 300 |
|
| 760 |
|
| 580 |
|
| 0 |
|
General factory (MHs) |
| 3,900 |
|
| 8,800 |
|
| 2,500 |
|
| 6,300 |
|
Using the ABC data, determine the total amount of overhead cost assigned to each product.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started