Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16
Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16 days. Determine the expected processing time for the activity.
Select one:
a.3.16
b.5.16
c.10
d.5.33