Question
t o t ml t p t e A-----135 BA222 CA111 DB000 EC,D 234 FC,D 111 GF111 HE, G111 1) Construct a PERT network. [NOTE:
to tml tp te
A-----135
BA222
CA111
DB000
EC,D 234
FC,D 111
GF111
HE, G111
1) Construct a PERT network.
[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]
2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.
3) Find the completion time and the standard deviation () for the project round off the standard deviation to the nearest hundredth:twodecimal places.
4) What is the likelihood of this project being completed earlier than6days?
5) Between7and9days?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started